Disability Access to Streets and Sidewalks - Curb Ramps
Federal contribution
$496,594
Federal share25%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Jul 12, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 30, 2010
- Construction end3 weeks earlyforecast Jul 30, 2011
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39382 in the federal list. How to read these figures.