New Sidewalks for Pedestrian Collector Routes

Vancouver, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,405,156
Federal share28%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
201020112012
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
May 21, 2010(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 31, 2011

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39383 in the federal list. How to read these figures.