Upper Trout Lake West Sewer Separation

Vancouver, British Columbia

completeWastewaterISF
Federal contribution
$3.3M
$3,333,300
Federal share33%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Mar 1, 2010(actual)
Construction end
Apr 15, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 1, 2010
  • Construction end2 weeks lateforecast Mar 31, 2011