Highway 97C - Coldwater Interchange to Brake Check
Federal contribution
$863,000
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 15, 2010
Also in Merritt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39395 in the federal list. How to read these figures.