Lower Nicola Indian Band - Community Solar Gardens

Merritt, British Columbia

completeGreen EnergyGIS
Federal contribution
$738,950
Federal share75%

of $985.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2020
20212022202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Lower Nicola Indian Band
Construction start
Mar 1, 2022(actual)
Construction end
Jun 30, 2025(actual)

Against the original forecast

  • Construction end4 weeks lateforecast May 30, 2025