Coldwater Avenue Infrastructure Improvements

Merritt, British Columbia

completeWastewaterCWWF
Federal contribution
$1.4M
$1,384,517
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Merritt
Construction start
Apr 10, 2017(actual)
Construction end
Mar 25, 2019(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jul 31, 2017
  • Construction end7 months lateforecast Aug 31, 2018

Also in Merritt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47690 in the federal list. How to read these figures.