Highway 3A - Nelson Westbound Passing Lane
Federal contribution
$2.7M
$2,721,000
Federal share50%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- May 15, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 31, 2010
Also in Nelson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39406 in the federal list. How to read these figures.