Hall Street Corridor - Phase II
Federal contribution
$2.2M
$2,220,508
Federal share33%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 11, 2017
20182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Nelson
- Construction start
- Oct 5, 2017(actual)
- Construction end
- Apr 30, 2019(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 7, 2017
- Construction end5 months lateforecast Nov 30, 2018