Hall Street Corridor - Phase II

Nelson, British Columbia

completeHighways and RoadsSCF
Federal contribution
$2.2M
$2,220,508
Federal share33%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
20182019
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Nelson
Construction start
Oct 5, 2017(actual)
Construction end
Apr 30, 2019(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 7, 2017
  • Construction end5 months lateforecast Nov 30, 2018