Nelson Exchange
Federal contribution
$743,066
Federal share40%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 30, 2023
202320242025
Built
Approved 14 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Apr 10, 2025(actual)
- Construction end
- Sep 1, 2025(actual)
Against the original forecast
- Construction end5 weeks lateforecast Jul 31, 2025
Also in Nelson