English Bay Seawall Improvements - English Bay to Sunset Beach
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Aug 9, 2010(actual)
- Construction end
- May 30, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 26, 2010
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39419 in the federal list. How to read these figures.