Back to projects

Neighbourhood Energy Utility - Distribution System Extension

Vancouver, British Columbia

completeBrownfield Remediation And RedevelopmentISF
Federal contribution
$700,000
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Jun 1, 2010(actual)
Construction end
Oct 28, 2011(actual)

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39420 in the federal list. How to read these figures.