Back to projects

Relocation of the Vancouver Main Street Police Station

Vancouver, British Columbia

completeAdministration, Emergency and Public WorksISF
Federal contribution
$4.6M
$4,570,534
Federal share30%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 18, 2010
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Apr 9, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 1, 2010

Also in Vancouver