Annacis Island Wastewater Treatment
Federal contribution
$3.0M
$3,000,000
Federal share33%
of $9.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 12, 2010
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of Greater Vancouver
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Sep 16, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Aug 15, 2010
- Construction end2 weeks earlyforecast Sep 30, 2011
Also in Delta
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39427 in the federal list. How to read these figures.