Alex Fraser Bridge

Delta, British Columbia

completeHighways and RoadsNRP
Federal contribution
$31.6M
$31,609,574
Federal share50%

of $63.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 19, 2017
20172018201920202021
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Dec 4, 2017(actual)
Construction end
Feb 28, 2021(actual)

Against the original forecast

  • Construction end3 months lateforecast Nov 30, 2020

Also in Delta

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47645 in the federal list. How to read these figures.