Highway 91 to Highway 17 and Deltaport Way Corridor Improvement
Federal contribution
$81.7M
$81,671,139
Federal share35%
of $235.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 10, 2017
2017201920212023
Built
Approved 2 weeks before the announcement.
- Program
- National Infrastructure Component
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Sep 12, 2018(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction end6 months earlyforecast Sep 30, 2023
Also in Delta
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46343 in the federal list. How to read these figures.