Highway 88 - Roadwork

Mackenzie County, Alberta

completeHighways and RoadsISF
Federal contribution
$4.3M
$4,349,047
Federal share50%

of $8.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
May 26, 2010(actual)
Construction end
Oct 14, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 15, 2010
  • Construction end6 months earlyforecast Mar 31, 2011