Mackenzie County Rural Potable Water Infrastructure

Mackenzie County, Alberta

completeDrinking WaterSCF
Federal contribution
$1.8M
$1,764,033
Federal share33%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
County of Mackenzie
Construction start
Jun 1, 2016(actual)
Construction end
Aug 17, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2016
  • Construction end8 months lateforecast Dec 31, 2016