Paving Highway 88

Mackenzie County, Alberta

completeHighways and RoadsISF
Federal contribution
$1.7M
$1,743,830
Federal share48%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
May 26, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Mackenzie County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39770 in the federal list. How to read these figures.