Silent Lake Park Shelter Construction

Highlands East, Ontario

completeRecreationISF
Federal contribution
$43,297
Federal share48%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Nov 8, 2010(actual)
Construction end
Feb 4, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 15, 2010
  • Construction end8 weeks earlyforecast Mar 31, 2011

Also in Highlands East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39697 in the federal list. How to read these figures.