Back to projects

Construction of a community centre and arena parking lot

Bromont, Quebec

completeRecreationCC Top Up
Federal contribution
$91,601
Federal share27%

of $338.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Bromont
Construction start
Aug 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end7 months lateforecast Sep 1, 2010

Also in Bromont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39726 in the federal list. How to read these figures.