Reinforcement of sports and recreational infrastructures at McMasterville Ensoleillé Park

McMasterville, Quebec

completeSportCC Top Up
Federal contribution
$1.7M
$1,738,178
Federal share33%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 8, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Aug 2, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 1, 2010

Also in McMasterville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39792 in the federal list. How to read these figures.