Back to projects

Program for the renewal of drinking water and wastewater pipes

McMasterville, Quebec

completeWastewaterISF
Federal contribution
$91,917
Federal share31%

of $296.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 27, 2010
20102011
Built

Approved 8 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 9, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009

Also in McMasterville