Installation of a Refrigeration System at the Municipal Skating Rink
Federal contribution
$594,089
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2017
2017201820192020
Built
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of McMasterville
- Construction start
- May 24, 2017(actual)
- Construction end
- Jan 15, 2020(actual)
Against the original forecast
- Construction start2 months earlyforecast Aug 7, 2017
- Construction end2.3 years lateforecast Sep 29, 2017
Also in McMasterville
- Reinforcement of sports and recreational infrastructures at McMasterville Ensoleillé Park$1.7M
- Infrastructure repairs to Constable Blvd., Morin and Jarry Streets$1.4M
- Program for the renewal of drinking water and wastewater pipes$455.1K
- Program for the renewal of drinking water and wastewater pipes$91.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47744 in the federal list. How to read these figures.