Highway 17 - East and West of Kenora
Federal contribution
$2.5M
$2,498,977
Federal share41%
of $6.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Mar 21, 2011(actual)
Against the original forecast
- Construction end6 months lateforecast Sep 24, 2010
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39799 in the federal list. How to read these figures.