Highway 17 - East and West of Kenora

Kenora, Ontario

completeHighways and RoadsISF
Federal contribution
$2.5M
$2,498,977
Federal share41%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
2011
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Aug 9, 2010(actual)
Construction end
Mar 21, 2011(actual)

Against the original forecast

  • Construction end6 months lateforecast Sep 24, 2010

Also in Kenora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39799 in the federal list. How to read these figures.