Water Treatment Plant Upgrades
Federal contribution
$1.3M
$1,333,333
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Naotkamegwanning First Nation
- Construction start
- Jun 19, 2018(actual)
- Construction end
- Sep 13, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 16, 2018
- Construction end4 months lateforecast May 1, 2019
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46867 in the federal list. How to read these figures.