Back to projects

Water Treatment Plant Upgrades

Kenora, Ontario

completeDrinking WaterSCF
Federal contribution
$1.3M
$1,333,333
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
201720182019
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 19, 2018(actual)
Construction end
Sep 13, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 16, 2018
  • Construction end4 months lateforecast May 1, 2019

Also in Kenora