Water Treatment Plant at Kejick Bay

Kenora, Ontario

completeDrinking WaterSCF
Federal contribution
$1.8M
$1,810,000
Federal share33%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2015
2016201720182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Lac Seul First Nation
Construction start
Aug 30, 2018(actual)
Construction end
Aug 30, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2018
  • Construction end7 months earlyforecast Mar 31, 2020