Construction of a multifonctional centre
Federal contribution
$987,921
Federal share32%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2010
201020112012
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Adstock
- Construction start
- Oct 14, 2010(actual)
- Construction end
- Jan 26, 2012(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2010
- Construction end9 months lateforecast Apr 15, 2011
Also in Adstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39872 in the federal list. How to read these figures.