Renewal of water pipes
Federal contribution
$996,279
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201720182019
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Adstock
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Sep 27, 2019(actual)
Against the original forecast
- Construction start14 months lateforecast Sep 5, 2016
- Construction end3 months lateforecast Jul 1, 2019
Also in Adstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48888 in the federal list. How to read these figures.