Back to projects

Renewal of water pipes

Adstock, Quebec

completeDrinking WaterCWWF
Federal contribution
$996,279
Federal share50%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201720182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Adstock
Construction start
Nov 1, 2017(actual)
Construction end
Sep 27, 2019(actual)

Against the original forecast

  • Construction start14 months lateforecast Sep 5, 2016
  • Construction end3 months lateforecast Jul 1, 2019

Also in Adstock

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48888 in the federal list. How to read these figures.