Upgrading of the Ostiguy Water Supply System (Lac Jolicoeur)
Federal contribution
$265,512
Federal share48%
of $549.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201720182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Adstock
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Jul 26, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2017
- Construction end4 weeks lateforecast Jul 1, 2019
Also in Adstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48938 in the federal list. How to read these figures.