Schedule

Announced and approvedMar 17, 2017
201720182019
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Adstock
Construction start
Nov 1, 2017(actual)
Construction end
Jul 26, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 1, 2017
  • Construction end4 weeks lateforecast Jul 1, 2019