Reorganisation and enlargement of the multisport center and construction of the aquatic center
Federal contribution
$4.1M
$4,142,167
Federal share33%
of $12.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2010
2011
Built
Approved 5 months before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Drummondville
- Construction start
- May 4, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2010
Also in Drummondville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39875 in the federal list. How to read these figures.