Drummondville Exhibition Centre
Federal contribution
$6.5M
$6,501,662
Federal share33%
of $19.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2010
ApprovedMar 25, 2011
20112012201320142015
Built
Approved 4 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Société de développement économique de Drummondville
- Construction start
- Sep 16, 2013(actual)
- Construction end
- Feb 19, 2015(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 30, 2013
- Construction end6 weeks earlyforecast Mar 31, 2015
Also in Drummondville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40896 in the federal list. How to read these figures.