Construction of a drinking water treatment plant - Drummondville

Drummondville, Quebec

completeDrinking WaterGIS
Federal contribution
$16.1M
$16,119,999
Federal share40%

of $40.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 12, 2021
20212022202320242025
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Drummondville
Construction start
Jan 17, 2022(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction end5 months earlyforecast Jun 13, 2025

Also in Drummondville