Back to projects

Rehabilitation of four tennis courts

L'Ancienne-Lorette, Quebec

completeSportCC Top Up
Federal contribution
$140,302
Federal share30%

of $468.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2010
2011
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of L'Ancienne-Lorette
Construction start
Sep 15, 2010(actual)
Construction end
Jun 4, 2011(actual)

Also in L'Ancienne-Lorette