Knight Street Bridge Seismic Upgrade
Federal contribution
$694,872
Federal share22%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
2011
Built
Approved 5 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Translink
- Construction start
- Mar 30, 2011(actual)
- Construction end
- Oct 28, 2011(actual)
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40241 in the federal list. How to read these figures.