Highway 19 - Mohun Bridge no. 1515 and Lukwa River Bridge no. 2595

Campbell River, British Columbia

completeHighways and RoadsISF
Federal contribution
$321,406
Federal share50%

of $642.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
Built

Approved 5 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 4, 2010(actual)
Construction end
May 14, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast May 28, 2010