East Hants Sportsplex
Federal contribution
$2.0M
$2,000,000
Federal share13%
of $15.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 28, 2011
20112012
Built
Approved 7 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- East Hants Arena Association
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Jul 5, 2012(actual)
Also in East Hants
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40255 in the federal list. How to read these figures.