East Hants Aquatic Centre
Federal contribution
$5.5M
$5,499,266
Federal share33%
of $16.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2017
201820192020202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Municipality of East Hants
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Mar 14, 2023(actual)
Against the original forecast
- Construction start10 months lateforecast Aug 1, 2017
- Construction end15 months lateforecast Nov 30, 2021
Also in East Hants
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49967 in the federal list. How to read these figures.