Shubenacadie Wastewater Treatment Plant Replacement

East Hants, Nova Scotia

completeWastewaterGIS
Federal contribution
$1.9M
$1,920,000
Federal share40%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
2021202220232024
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of East Hants
Construction start
May 3, 2021(actual)
Construction end
Jun 30, 2024(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 2, 2021
  • Construction end4 weeks earlyforecast Jul 31, 2024