Resurfacing of Highway 1 from East of Provincial Road 240 to West of Provincial Road 240
Federal contribution
$500,000
Federal share10%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2010
Built
Approved 5 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Nov 8, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2010
- Construction end5 weeks earlyforecast Dec 15, 2010
Also in Portage la Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40910 in the federal list. How to read these figures.