Back to projects

Route 111 Rehabilitation

Saint John, New Brunswick

completeHighways and RoadsISF
Federal contribution
$497,670
Federal share45%

of $1.1M total eligible cost; the rest comes from other partners.

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Sep 15, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 30, 2010

Also in Saint John