Route 111 Rehabilitation
Federal contribution
$497,670
Federal share45%
of $1.1M total eligible cost; the rest comes from other partners.
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 30, 2010
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40917 in the federal list. How to read these figures.