Back to projects

Spruce Lake Industrial Park Watermain Installation

Saint John, New Brunswick

completeDrinking WaterISF
Federal contribution
$145,549
Federal share16%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2010
2011
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saint John
Construction start
Nov 1, 2010(actual)
Construction end
Feb 28, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 7, 2010
  • Construction end4 weeks earlyforecast Mar 31, 2011

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40923 in the federal list. How to read these figures.