Cottage Hill and Rockwood Water Storage Reservoir
Federal contribution
$134,191
Federal share22%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2010
Built
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Nov 29, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 27, 2010
- Construction end3 months earlyforecast Mar 31, 2011
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40925 in the federal list. How to read these figures.