Road Resurfacing

Saint John, New Brunswick

completeHighways and RoadsISF
Federal contribution
$879,745
Federal share23%

of $3.8M total eligible cost; the rest comes from other partners.

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saint John
Construction start
Aug 25, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 19, 2010

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40926 in the federal list. How to read these figures.