Omands Creek Park Active Transportation
Federal contribution
$105,049
Federal share23%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedAug 11, 2010
20102011
Built
Approved 11 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 8, 2011(actual)
- Construction end
- Nov 16, 2011(actual)
Against the original forecast
- Construction end4 weeks lateforecast Oct 21, 2011
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40985 in the federal list. How to read these figures.