Pathway Rehabilitation on Jockvale Road
Federal contribution
$69,734
Federal share23%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 3, 2011
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Nov 24, 2010(actual)
- Construction end
- Jul 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Oct 22, 2010
- Construction end4 weeks lateforecast Jun 30, 2011
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41042 in the federal list. How to read these figures.