Renovation of the Ruth E. Dickinson Library
Federal contribution
$163,488
Federal share30%
of $550.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 3, 2011
2011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Feb 21, 2011(actual)
- Construction end
- Jul 15, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 6, 2010
- Construction end2 weeks lateforecast Jun 30, 2011