Elevator Upgrades at the Kanata Recreation Complex

Ottawa, Ontario

completeRecreationISF
Federal contribution
$74,567
Federal share29%

of $255.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 3, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Jan 17, 2011(actual)
Construction end
Aug 10, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Dec 13, 2010
  • Construction end3 months earlyforecast Oct 30, 2011

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41063 in the federal list. How to read these figures.