Redesign of the Bob MacQuarrie Visual Arts Studio

Ottawa, Ontario

completeRecreationISF
Federal contribution
$99,289
Federal share25%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 3, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
May 30, 2011(actual)
Construction end
Oct 23, 2011(actual)