New Change Room at the Tom Brown Arena
Federal contribution
$45,444
Federal share27%
of $170.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 3, 2011
2011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Mar 7, 2011(actual)
- Construction end
- Jul 29, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jan 10, 2011