New Change Room at the Manotick Arena

Ottawa, Ontario

completeSportISF
Federal contribution
$54,905
Federal share32%

of $170.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 3, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Mar 1, 2011(actual)
Construction end
Jul 12, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jan 10, 2011
  • Construction end2 weeks earlyforecast Jul 29, 2011

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41080 in the federal list. How to read these figures.